|
 |
- Analyzed a claim on a $19 million, 200-unit low-income housing project.
The claim was for extended overhead damages due to a 4.5-month project
delay. Performed a detailed study of contractor field and home office
overheads. Formulated and presented settlement methodology which resulted in
the successful settlement of the claim.
- Evaluated a $2.1 million claim on a housing rehabilitation project. The
claim consisted of home office costs, field office costs, inefficiency,
professional and consultant costs, unpaid contract amount, and other claims.
Disclosed as cost/schedule expert witness. Presented findings in mediation;
case was settled in post-mediation negotiations.
- Analyzed three subcontractor claims totaling over $1 million on
a public housing project. Presented findings in successful mediation with
mechanical subcontractor. Represented client in negotiation sessions with
several subcontractors as schedule/cost expert.
|
|